Skip to main content
Version: 1.3

FDS Validation (NUREG 1934 Appendix B)

FDS Validation (NUREG 1934 Appendix B)

This case runs the U.S. NRC NUREG-1934 (EPRI 1023259), Appendix B — Cabinet Fire in a Switchgear Room through FRI3D's FDS pipeline, and compares it with NRC's own FDS deck for the case, both run in FDS 6.7.9. It is the FDS counterpart of the CFAST Appendix B validation, and extends the FDS Appendix A validation to a scenario with fire growth and spread.

FRI3D generates the FDS input from the plant model alone. During the run, FDS decides when the cable trays above the cabinet ignite and when their cables fail:

  • The lowest tray ignites when the cabinet fire's flames reach it. FRI3D computes that time from the fire's heat-release curve. Alternatively, FDS's own THIEF cable in the tray failing first also ignites it.
  • The trays above follow the FLASH-CAT stack schedule (NUREG/CR-7010).
  • Each cable fails when FDS's THIEF cable model, read 2 mm inside the jacket, reaches the failure temperature (NUREG/CR-6931 Vol. 3).

At a glance

EventFRI3D FDSNRC FDSDifference
Lowest tray (3.9 m) ignites472 s553 s−81 s
Middle tray (4.4 m) ignites712 s793 s−81 s
Top tray (4.9 m) ignites892 s973 s−81 s
Lowest tray's cable reaches 205 °C560 s553 s+7 s
Middle tray's cable reaches 205 °C749 s711 s+38 s
Top tray's cable reaches 205 °C834 s883 s−49 s
Heat release at 1200 s1476 kW1493 kW−1 %
Adjacent cabinetsnot damagednot damaged—
  • Ignition. Both decks use the same FLASH-CAT schedule. They differ only in what lights the lowest tray. FRI3D lights it when the flames reach it, at 472 s, close to the 480 s NUREG-1934 gives for the same event. NRC's FDS deck waits for the cable under the tray to fail, at 553 s. So FRI3D's whole sequence runs 81 s ahead.
  • Cables. The lowest tray's cable fails within 7 s of NRC's. The middle and top trays' cables fail 38 s later and 49 s earlier. A grid study shows why: those cables are heated by another tray's flames, which FRI3D's 0.2 m grid resolves less sharply than NRC's 0.1 m grid around the trays. With a 0.1 m mesh around the trays, FRI3D's deck brings the top tray's cable failure to within 5 s of NRC's and the middle tray's to within 47 s, counted from when the lowest tray ignites.
  • Heat release and gas temperatures agree closely; the differences follow from the earlier ignition.

Reference case

The same room and fire as the CFAST Appendix B case:

  • a 464 kW electrical cabinet fire in a 26.5 × 18.5 × 6.1 m switchgear room with 0.5 m concrete walls, floor and ceiling;
  • three horizontal cable trays stacked 0.5 m apart above the cabinet;
  • three supply and three return fans; the room is otherwise sealed.

The two FDS decks:

ItemNRC FDS deckFRI3D FDS deck
SourceNUREG-1934 CD, Switchgear_Room_Cabinet.fds (FDS 5), converted to FDS 6generated from FRI3D's NUREG-1934 Appendix B validation model
Cabinet fire464 kW, t² growth to 720 s, steady to 1200 ssame
Grid752,040 cells: 0.1 m around the fire and trays, 0.2 × 0.2 × 0.1 m elsewhere576,000 cells, 0.2 m
Simulated time1200 s1200 s
SolverFDS 6.7.9, 3 MPI processesFDS 6.7.9, 8 OpenMP threads

NRC's deck was written for FDS 5. To run it in FDS 6 its cable model and combustion inputs were converted, keeping NRC's values. NUREG-1934 reports the lowest tray's cable failing at about 495 s in FDS 5; in FDS 6 it fails at 553 s. FRI3D is compared with the FDS 6 run, so both decks run the same solver.

Secondary ignition (FLASH-CAT)

Both decks model the burning trays the same way: a strip of each tray burns at a fixed heat release per unit area, and the burning area spreads along the tray in both directions.

ItemNRC FDS deckFRI3D FDS deck
Lowest tray igniteswhen the THIEF cable under it reaches 205 °Cwhen the flames reach it (computed: 472 s), or when the THIEF cable under it reaches 200 °C, whichever is first
Middle tray ignites240 s after the lowest tray240 s after the lowest tray (FLASH-CAT: +4 min)
Top tray ignites420 s after the lowest tray420 s after the lowest tray (FLASH-CAT: +3 min more)
Initial burning length (low / middle / top)0.6 / 1.4 / 2.0 m0.42 / 1.12 / 1.82 m
Spread rate along the tray0.89 mm/s0.89 mm/s
Cable heat release per unit area250 kW/m²250 kW/m²
Burning of each tray segmentfull after 127 s, out at 762 sfull after 134 s, out at 805 s
  • The initial burning length widens up the stack in both decks (FLASH-CAT's 35° spread). FRI3D starts from the width of its modelled fire and widens by 0.7 m per tray (0.5 m × tan 35° on each side). NRC starts from a 0.6 m strip and widens by 0.8 m, then 0.6 m.
  • FRI3D computes each tray's burning time from the cable mass and heat of combustion in its cable library; it comes out 6 % longer than the time NRC's deck states.

Ignition times:

TrayFRI3D FDSNRC FDSNRC CFAST deck (prescribed)FRI3D CFAST
3.9 m472 s553 s480 s482 s
4.4 m712 s793 s720 s722 s
4.9 m892 s973 s900 s902 s

What lit FRI3D's lowest tray:

CriterionFirst reached
Flame tip reaches the lowest tray472 s
THIEF cable under the lowest tray reaches 200 °C550 s

FRI3D's flame-reach time agrees with the 480 s that NUREG-1934 and NRC's CFAST deck use. NRC's FDS deck lights the tray on its cable instead, which takes 81 s longer.

Results

Heat release rate

TimeFRI3D FDSNRC FDSDifference
300 s81 kW81 kW0 %
480 s212 kW207 kW+2 %
600 s398 kW363 kW+10 %
720 s571 kW597 kW−4 %
900 s869 kW877 kW−1 %
1000 s1229 kW1036 kW+19 %
1100 s1390 kW1437 kW−3 %
1200 s1476 kW1493 kW−1 %
  • Up to the first tray ignition the two decks burn the same cabinet fire.
  • FRI3D lights each tray 81 s earlier, so it leads while a tray's fire grows (600 s, 1000 s). NRC catches up once the same tray is burning in both (720 s, 900 s, 1100 s), and then runs slightly higher because its deck starts each tray with a longer burning strip.

THIEF cable temperatures

TrayFRI3D THIEF cable heightFRI3D reaches 205 °CNRC THIEF cable heightNRC reaches 205 °CDifference
3.9 m3.7 m560 s3.8 m553 s+7 s
4.4 m4.3 m749 s4.3 m711 s+38 s
4.9 m4.7 m834 s4.8 m883 s−49 s
  • Both decks place each THIEF cable just under its tray, above the cabinet fire, and read its temperature 2 mm inside the jacket.
  • Lowest tray. Before it ignites, only the cabinet fire's plume heats its cable, and the two decks agree within 1 °C. The cable fails within 7 s of NRC's.
  • Middle tray. Its cable fails before its own tray burns, heated by the lowest tray's flame 0.3 m below. FRI3D's flame starts 81 s earlier, but the cable heats at about a third of NRC's rate, so it fails 38 s later.
  • Top tray. The same slower heating, but FRI3D's earlier middle-tray fire outweighs it, so the cable fails 49 s earlier.
  • Once the trays burn, FRI3D's cables stay 100–160 °C cooler than NRC's.

Grid study

FRI3D's deck was run again with a single change: a 0.1 m mesh around the fire and the tray stack, as NRC's deck has. The lowest tray was lit the way NRC's deck lights it, on its cable, so both follow the same sequence. Like the other two runs, it covers 1200 s.

FRI3D, 0.2 m gridFRI3D, 0.1 m around the fireNRC
Lowest tray's cable 91 s after the tray ignites206 °C319 °C304 °C
Middle tray's cable fails, after the lowest tray ignites278 s205 s158 s
Top tray's cable fails, after the lowest tray ignites362 s334 s329 s
Heat release at 1200 s1476 kW1431 kW1493 kW
  • With the finer mesh, FRI3D's deck heats the cable in its own tray's flame as fast as NRC's deck.
  • The middle tray's cable fails 205 s after the lowest tray ignites, against NRC's 158 s, closing 61 % of the gap. The remaining 47 s is consistent with NRC's room fire being larger at that point (578 against 506 kW), because NRC's deck lights the lowest tray later, into a bigger cabinet fire.
  • The top tray's cable fails 334 s after the lowest tray ignites, against NRC's 329 s. The finer mesh closes 85 % of the gap.
  • The heat release averages within 1 % of NRC's up to 900 s and ends 4 % below it (1431 against 1493 kW), because NRC's deck starts each tray with a longer burning strip. The 0.2 m run ends closer to NRC only because it lit its trays 81 s earlier.
  • Once the trays burn, the cables sit inside the tray flames, and their temperature depends on exactly where each cable is in the flame. With the finer mesh, FRI3D's peak cable temperatures are within about 100 °C of NRC's, two higher and one lower. This happens after the cables have failed, so it does not affect the failure times.

So the cable differences come from the grid around the trays, not from how FRI3D builds the deck. A 0.1 m mesh around a cable tray stack reproduces NRC's cable heating.

Hot gas layer

NRC's deck has no layer devices, so both decks' layers are computed the same way, from the same vertical plane through the fire, about 6 m to either side of it.

TimeLayer height, FRI3D / NRCUpper-layer temperature, FRI3D / NRC
300 s4.3 / 5.0 m23 / 23 °C
472 s3.3 / 4.0 m28 / 27 °C
720 s2.4 / 3.2 m41 / 38 °C
900 s2.2 / 2.6 m53 / 45 °C
1200 s1.9 / 2.2 m74 / 66 °C
  • Temperature agrees within 1–3 °C until the trays burn. After that FRI3D runs up to 9 °C warmer, because its trays lit earlier and it has released 5 % more heat by the end.
  • Height. FRI3D's layer sits 0.3–0.8 m lower, already before any tray burns. NRC's deck uses 0.1 m tall cells throughout the room, FRI3D's 0.2 m. Taller cells spread the boundary between the hot layer and the cool air below over more height, which reads as a lower layer. The walls, ventilation and fire are the same in both, and the finer mesh around the fire alone does not change the layer.
  • The cables and cabinets sit in the fire's plume and flames, so the layer height does not affect their results.

Failure validation

NRC's Appendix B case defines failure for two kinds of item: the cables in the three trays, as THIEF targets failing at 205 °C, and the cabinets next to the burning one, which NUREG-1934 concludes are not damaged. FRI3D's failures are compared against both. The tray (raceway) and burning-cabinet failures have no NRC counterpart, so FRI3D's CFAST result is shown for reference.

Cables

TrayFRI3D FDSNRC FDSNRC CFAST deck (THIEF target)FRI3D CFAST
3.9 m552 s553 s630 s537 s
4.4 m742 s711 s700 s640 s
4.9 m832 s883 s840 s835 s
  • The cables fail in stack order, within 1, 31 and 51 s of NRC's FDS deck.
  • FRI3D uses 200 °C, NUREG/CR-6931 Vol. 3's thermoplastic threshold, because the cable type in this model is unknown; NRC's deck uses 205 °C.

Cable trays

TrayFRI3D FDSFRI3D CFASTNRC
3.9 m677 s506 snot evaluated
4.4 m815 s624 snot evaluated
4.9 m816 s818 snot evaluated
  • A tray fails by the heat-soak method, which accumulates the tray's exposure to heat over time.
  • NRC evaluates the cables in the trays, not the trays themselves.
  • The two solvers compute that exposure differently: FDS from the temperatures and heat flux it resolves on the tray, CFAST from its fire-plume and smoke-layer formulas. FDS fails the lower two trays later than CFAST. The top tray, heated by both trays burning below it, fails at the same time in both.

Cabinets

CabinetFRI3D FDSNRC FDSFRI3D CFASTNRC CFAST deck
Burning cabinetfails at 232 snot evaluated (it is the fire)fails at 48 snot evaluated
Adjacent cabinetsnot damaged; surface peaks 95 / 85 °Cnot damaged; surface peaks 135 / 129 °Cnot damaged; peaks 143 / 139 °Cnot damaged; peak 137 °C
  • The adjacent cabinets stay well below the 205 °C damage threshold in both FDS decks, as NUREG-1934 concludes.
  • NRC's FDS deck reads the hottest point anywhere on the adjacent cabinet rows, including their tops, which face the hot layer and the burning trays. FRI3D reads a 0.4 m patch on the side of each cabinet facing the fire, so it reads cooler.
  • The burning cabinet's target sits just above the fire. CFAST's plume formula gives a flame temperature there even while the fire is very small (2 kW at 48 s). FDS spreads a small flame over a 0.2 m cell, so its target passes 205 °C once the fire has grown to about 50 kW, at 232 s.

Conclusion

From the plant model and the cable library alone, FRI3D's FDS pipeline writes the same secondary ignition logic as NRC's FDS deck: the same stack delays, spread rate and cable heat release. It ignites the lowest tray on flame reach, matching NUREG-1934's 480 s, where NRC's FDS deck waits for the cable to fail. Run in the same FDS version, the two decks agree on the heat release and on the lowest tray's cable failure within 7 s. The middle and top trays' cables fail within 50 s of NRC's, and a grid study shows the remaining difference comes from the mesh resolution around the trays. The adjacent cabinets are not damaged, as NUREG-1934 concludes.

Reference

  • NUREG-1934 / EPRI 1023259, Nuclear Power Plant Fire Modeling Analysis Guidelines, Appendix B: Cabinet Fire in a Switchgear Room.
  • NUREG/CR-7010 Vol. 1, Cable Heat Release, Ignition, and Spread in Tray Installations During Fire (CHRISTIFIRE), Phase 1: Horizontal Trays, §9.2: the FLASH-CAT model.
  • NUREG/CR-6931 Vol. 3, Cable Response to Live Fire (CAROLFIRE), Volume 3: Thermally-Induced Electrical Failure (THIEF) Model.

Reach out

If you need help after reading this doc, email us [email protected] for an answer.